Yuhang District Chongxian to old Yuhang connection line elevated project

       Yuhang District Chongxian to old Yuhang connection line elevated project belongs to the 2022 Hangzhou Asian Games key supporting facilities project, the route length of 34.0 km, the total length of this bid section 3.57 kilometers, the total length of steel beam 664 meters, steel plate Q345C and Q390C material, a total of 7300 tons of steel。
       The project won the "Zhejiang Steel Structure Diamond Award"